Dolna Odra, Poland
XL4 penstock
From May 2020 to spring 2023, we delivered the following penstocks for the new power plant in Dolna-Odra:
Important facts:
+ 8x XL4 penstock 3500 × 4500 mm with 10 mWs
Dolna Odra, Poland
XL4 penstocks 3500 x 4500 mm, 10 mWs
From May 2020 to spring 2023, we delivered the following penstocks for the new power plant in Dolna-Odra:
Important facts:
+ 8x XL4 penstock 3500 × 4500 mm with 10 mWs
Gaildorf, Germany
XL4 double-plate penstock
The Gaildorf 2018 natural power storage pilot project is breaking new ground, which requires individualized products - BÜSCH accompanies you from planning and design to production and assembly.
The first BÜSCH delivery could be inspected at the end of 2018 in the already installed condition. A custom-made double-plate penstock (2000 × 5000 mm) with independently moving plates. This is located in an inlet and outlet structure that regulates the water balance of the power plant - once between the lower reservoir and the adjacent river Kocher and also between the lower reservoir and the pump turbines.
Important facts:
+ XL4 double-plate penstock 2000 × 5000 mm
Żerań, Poland
XL3 channel penstock 5600 x 3600 mm
The Żerań combined heat and power plant in Warsaw, built in the mid-1950s, is one of the largest combined heat and power plants in Poland and generates both electricity and district heating. In order to be able to continue to operate the longest district heating network in Central Europe reliably in the future, modernization measures are constantly being implemented. Our XL4 penstocks meet an absolute tightness according to EN 12266 and can withstand a pressure of 1.0 bar with a water column of 10 m.
Important facts:
+ 10x XL4 penstock 2400 × 2500 mm with penstock frame
+ integrated 6x Bar screen
+ 4x XL3 channel penstock 5600 × 3600 mm
+ 16x BEA©servo electric actuators - custom designed
+ 3x Stop logs
Żerań, Poland
BEA©servo electric actuators
The Żerań combined heat and power plant in Warsaw, built in the mid-1950s, is one of the largest combined heat and power plants in Poland and generates both electricity and district heating. In order to be able to continue to operate the longest district heating network in Central Europe reliably in the future, modernization measures are constantly being implemented. Our XL4 penstocks meet an absolute tightness according to EN 12266 and can withstand a pressure of 1.0 bar with a water column of 10 m.
Important facts:
+ 10x XL4 penstock 2400 × 2500 mm with penstock frame
+ integrated 6x Bar screen
+ 4x XL3 channel penstock 5600 × 3600 mm
+ 16x BEA©servo electric actuators - custom designed
+ 3x Stop logs
Żerań, Poland
XL4 penstock mit BEA©servo electric actuators
The Żerań combined heat and power plant in Warsaw, built in the mid-1950s, is one of the largest combined heat and power plants in Poland and generates both electricity and district heating. In order to be able to continue to operate the longest district heating network in Central Europe reliably in the future, modernization measures are constantly being implemented. Our XL4 penstocks meet an absolute tightness according to EN 12266 and can withstand a pressure of 1.0 bar with a water column of 10 m.
Important facts:
+ 10x XL4 penstock 2400 × 2500 mm with penstock frame
+ integrated 6x Bar screen
+ 4x XL3 channel penstock 5600 × 3600 mm
+ 16x BEA©servo electric actuators - custom designed
+ 3x Stop logs
Jaworzno, Poland
XL3 channel penstock
The special fittings without housing are used in the cooling water circuit after the cooling tower. During maintenance work, they reliably prevent the cooling water from flowing back into the pump station and must therefore be driven reliably. The dimensions of the slides, higher torques and the longer operating times of more than two hours had to be mapped Which ultimately resulted in a completely new control technology
Important facts:
+ 4x XL3 channel penstock 5600 × 3600 mm
+ BEA©servo electric actuator - custom designed
Jaworzno, Poland
BEA©servo electric actuator
The special fittings without housing are used in the cooling water circuit after the cooling tower. During maintenance work, they reliably prevent the cooling water from flowing back into the pump station and must therefore be driven reliably. The dimensions of the slides, higher torques and the longer operating times of more than two hours had to be mapped Which ultimately resulted in a completely new control technology
Important facts:
+ 4x XL3 channel penstock 5600 × 3600 mm
+ BEA©servo electric actuator - custom designed
Jaworzno, Poland
XL3 channel penstock
The special fittings without housing are used in the cooling water circuit after the cooling tower. During maintenance work, they reliably prevent the cooling water from flowing back into the pump station and must therefore be driven reliably. The dimensions of the slides, higher torques and the longer operating times of more than two hours had to be mapped Which ultimately resulted in a completely new control technology
Important facts:
+ 4x XL3 channel penstock 5600 × 3600 mm
+ BEA©servo electric actuator - custom designed